Plant and crew
Paver and screed, delivery fleet, rollers, joint crew and survey. Select a feeder where the delivery method warrants one.
Estimate in t placed.
Release the paving interface, place the wearing lift to the intended profile, compact and finish joints and tie-ins.
Paver and screed, delivery fleet, rollers, joint crew and survey. Select a feeder where the delivery method warrants one.
Measure accepted area and thickness by mix. Convert to tonnes using compacted density and reconcile against supply tickets.
Issue test and survey records plus traffic release status to the markings and handover teams.
Do not use nominal paver capacity as achieved output. Check hot haul, closure length, joints and roller coverage.
Test the paving train bottleneckIncoming release · Tack coat and asphalt interface
Feeds · Line marking and raised pavement markers · Lot reconciliation and reopening
Incoming release · Tack coat and asphalt interface
Feeds · Line marking and raised pavement markers · Lot reconciliation and reopening
| Reference activity | Source unit | Low | Typical | High | Source |
|---|---|---|---|---|---|
| PRD.PV.013 Asphalt AC10 wearing course - by thickness (m2) | m2/hr (at 40 mm lift) | 300 | 600 | 1100 | S-061 |
| PRD.PV.014 Asphalt AC14 - by thickness (m2) | m2/hr (at 50 mm lift) | 300 | 600 | 1100 | S-061 |
| PRD.PV.016 Asphalt - supply + lay + compact (tonnage basis) | t/hr (paver-and-crew limited; ≈ 350-650 t/day) | 40 | 60 | 85 | S-061 |
| PRD.PV.017 Heavy-duty asphalt (EME2 / high-modulus / SMA) | t/hr (tighter temperature/compaction control) | 35 | 55 | 75 | S-061 |
Indicative bands. Match the activity, volume basis, lift or depth and time denominator to the lot. For a daily band, establish the original shift basis before converting to productive hours.
Use the contract edition, annexures and inspection plan for measurement and acceptance on a project.
Take quantities off the PDF drawings in Spark, then build the rate from labour, plant, materials and productivity in Trinity.